NAVFAC - Guam - U.S. Territory

2D and 3D CAD Files to be Used with the Contractors
Mulitiple Finish Grade Surfaces
2 Stormwater Detention Basis
Stormpiping
2D and 3D CAD Files to be Used with the Contractors
Mulitiple Finish Grade Surfaces
2 Stormwater Detention Basis
Stormpiping
Project Info: 

The 32 acre site located on a former World War II battlefield is being constructed by Watts Constructors.  Ashley & Vance Engineering provided construction support for GPS positioning related to earth work, piping, and site features. 

Project Features:

  • Over one mile new road
  • 2 stormwater detention basis
  • stormpiping
  • generator building
  • 28 structures

Our civil engineering group created 2D and 3D CAD files to be used with the Contractors Trimble GPS positioning equipment.  This included creation of mulitiple finish grade surfaces, and earth work excavation calculations.  This process allowed the Contractor to build the project safer, faster, resulting in significant cost savings for the Navy. 

Owner: U.S. Navy